Village disaster teams and volunteer groups prepare two Mount Merapi communities for eruptions through a government-led resilient village programme.
The Sleman Regency disaster management agency (BPBD Sleman) started the programme in Kepuharjo and Umbulharjo, two villages in Cangkringan District, Yogyakarta Special Region, with 8,669 residents in total. Each village has a disaster resilient village team that sits outside the village government but coordinates with it, with divisions for logistics, temporary barracks, public kitchens and evacuation. Its activities include contingency planning, risk mapping, early warning, training and simulations, and networking among volunteer groups. An independent 2024 study identified more than 50 volunteer networking groups in the villages and reports, based on an interview with the Kepuharjo village head, that residents and volunteers reacted quickly to the warning signs of the 2018 steam-driven (phreatic) eruption.
Mount Merapi (2,968 m) lies on the border between the Special Region of Yogyakarta and Central Java and is among Indonesia's most active volcanoes. The study behind this case lists eruptions in 1994, 1997, 1998, 2001, 2006 and 2010 and describes a recurrence of five to ten years. The October 2010 eruption was the most destructive. The study reports 367 deaths and about 400,000 people moved to evacuation areas, with 277 casualties and 2,271 destroyed buildings in Cangkringan District.
Kepuharjo (8 hamlets, 3,442 residents) and Umbulharjo (9 hamlets, 5,227 residents) lie on the southern slopes at 600 to 1,200 m, between about 4 and 10 km from the crater (the sources give different distances). After 2010, Sleman Regent Regulation No. 20 of 2011 divided the slopes into three disaster-prone areas. Nine hamlets in the highest-risk area, including Pelemsari in Umbulharjo and Kaliadem in Kepuharjo, were declared unfit for permanent housing, and relocated households received aid to build on 100 square metres of land elsewhere. Many residents still farm, quarry sand and run tourism ventures in the hazard zone, so living with recurring risk is a long-term condition.
The villages were designated as resilient villages in this setting. The programme began after the 2010 eruption and a village decree from 2014 established its resilient village team.
Hazard Type
Geographical Scope - Nuts
Geographical Scope
Population Size
Population Density
Needs Addressed
Communities on Merapi's southern slopes live close to a volcano that erupts every five to ten years, so preparedness has to be a permanent routine and not a response limited to the days around an eruption. After 2010 the authorities needed an organised structure in each village for evacuation, shelter, food supply and logistics, and the programme created one. Preparedness also depended on many small volunteer groups working with government agencies, which the programme tries to link through the village team and a district communication forum. Residents who stay in or near the hazard zone need regular training, risk mapping and early-warning routines. In Kepuharjo in 2017, a study points to gaps in equipment and communications: no landline telephones, no handheld radio in most households, an unstable signal near the volcano, and no evacuation vehicle or ambulance.
No public information on measures for specific vulnerable groups was found in the sources reviewed. The study names women's groups, children's health volunteers and youth groups among the volunteer groups. The national guideline for resilient villages asks for women and vulnerable groups to be represented in the village forum.
The programme follows a national framework: a 2018 study of Kepuharjo links it to the 2012 resilient village guideline of the BNPB (National Disaster Management Agency), which sets the criteria for assessing villages. Within that framework, initiation, funding and coordination sit at regency and village level. The Sleman Regency disaster agency started and coordinates the programme, the district government budget funds the village team according to the study, and village teams deliver it. National support is reported only for the Kepuharjo training, where BNPB provided part of the funding. Inside the locality the relationship is hierarchical: the study describes a top-down initiative that residents later took up and extended from the bottom up. Volunteer groups, the Yogyakarta Institute for Research and Technology Development of Geological Disaster (BPPTKG), which monitors the volcano, and village governments all take part, so the setting has multistakeholder features. Authority to start, fund and coordinate rests with government at regency and village level, not with the community and not with the national agency.
Contingency plans, volunteer teams, evacuation drills, temporary barracks and monitoring posts are in place according to the study. A 2018 article rated Kepuharjo as a mid-tier resilient village under the national criteria, meaning that plans and teams exist but the forum is not yet fully functioning and volunteer activity is not yet routine. No rating was found for Umbulharjo.
Residents and volunteers have built evacuation gathering points and monitoring posts with lighting, electricity and loudspeakers, and they keep evacuation routes clear. Hamlet-level lists record available vehicles and shelter supplies, and a community radio station broadcasts hazard information. Gaps reported for Kepuharjo in 2017 include missing landline coverage, too few handheld radios, and no evacuation vehicle or ambulance.
To turn a programme started by government into routine local practice. Residents and volunteers carry out preparedness tasks such as risk mapping, evacuation practice, early-warning relay, public kitchens and logistics, and they exchange information with the disaster agency and the volcano observatory. Engagement is two-way, but government agencies set the framework and lead coordination.
A village disaster team with working divisions; volunteer groups for youth, community protection, disaster preparedness, women and family welfare, and child health; a district communication forum for volunteer groups that meets every few months; hamlet-level data collection and mapping; training and simulations, including a preparedness parade; community radio; and communal work days known locally as gotong royong.
Residents and volunteers influence how preparedness is carried out in their hamlets, for example by mapping risks, building and maintaining evacuation facilities and running patrols when volcanic activity rises. The sources do not show that residents decided the programme's design, funding or priorities. The programme was started from above, funding comes from government budgets, and the Kepuharjo training was organised by government agencies with representatives from each hamlet attending.
In Kepuharjo, a two-day training is held once a year for hamlet representatives and volunteers. The December 2017 session drew 39 participants on the first day and 43 on the second, and covered disaster handling, command posts, shelters, first aid, public kitchens and a simulation. A budget of 150 million rupiah was set for the training, and participants received a transport allowance. A 2018 source notes that the training should be monthly but is annual because funds arrive late. Beyond formal training, the 2024 study reports informal learning inside volunteer groups, regular meetings of the district forum, and a community radio run with villagers, which keep skills and information circulating between events. No source reports how many people have been trained over the years or how skills are measured.
Vulnerable Groups
Governance
Emergency Preparedness
Infrastructure Readiness
Engagement Level
Empowerment Level
Implementation
A village disaster team set up next to, and not inside, the village government, with at least four working divisions.
A dense volunteer landscape: a 2024 study identified more than 50 networking groups, and names seven types of village volunteer group.
A district communication forum linking volunteer groups with BPBD, BPPTKG and the Red Cross.
Community radio (Gema Merapi FM), started by local activists after the 2010 eruption, used as a preparedness channel.
Household emergency bags and hamlet-level lists of vehicles and shelter supplies.
In Kepuharjo, an arrangement with safer villages (known as sister or buffer villages) to host evacuees under agreed procedures, reported in a 2018 study.
Preparedness practices tied to local custom, such as communal work and annual river-cleaning rituals.
Indonesian / No source states the languages of the programme's own materials.
The Sleman Regency disaster management agency (BPBD Sleman) started and coordinates the programme. The village governments and the village disaster teams of Kepuharjo and Umbulharjo carry it out day to day. The volcano observatory (BPPTKG) supports it with monitoring, and the national agency BNPB provides the framework and, for Kepuharjo training, part of the funding.
BPBD Sleman and BPPTKG are standing disaster and volcano-monitoring bodies with experience of Merapi. The village teams are newer, formed after the 2010 eruption, and Kepuharjo was rated mid-tier in 2017. No assessment of the implementers' experience was found in the sources reviewed.
BPBD Sleman; BPPTKG; BNPB; village governments and hamlet heads; the disaster resilient village teams; volunteer groups (Karang Taruna youth groups, Linmas community protection units, Tagana youth disaster teams, quick reaction and search-and-rescue teams, the PKK women and family welfare group, Posyandu child-health volunteers, the district communication forum, and community radio); the Indonesian Red Cross; and residents.
The sources do not set out a formal implementation plan, so the sequence below is reconstructed from them:
- After the 2010 eruption, the regency set disaster-prone areas by regulation and relocated households from the most dangerous hamlets.
- The villages were designated as resilient villages and a village team with working divisions was formed alongside the village government (Kepuharjo's team was established by village decree in 2014).
- Volunteer groups were organised or strengthened, and linked through a district communication forum.
- Programme activities were carried out: contingency plan making, community extension, early warning, mapping, inventories, logistics and food storage, training and simulations, local networking, and risk mapping.
- Training and drills were repeated, in Kepuharjo once a year, and households prepared emergency bags.
- The system was used in practice, for example during the 2018 phreatic eruption.
Government budget from the district, plus national and local government funds for the Kepuharjo training; volunteer time and communal labour; trainers and facilitators from BPBD and Tagana; a venue such as the village hall; transport allowances for trainees; evacuation barracks and shelter supplies; public kitchen equipment; communication equipment such as handheld radios, loudspeakers and a community radio; and vehicles for evacuation. Funding is domestic, but the Kepuharjo study reports delays when releasing funds.
No source gives a formal timeline. The programme began after the 2010 eruption, and the sources date it variously to 2011, 2012 and 2014. Activity continues: annual training was documented in December 2017, the 2018 phreatic eruption was handled through the system, and the 2024 study describes the programme as ongoing.
Experience of the Implementing Organisation in DRM
Target Audience
Resources Required
Timeframe & Phases
Participation Results
The authors of the 2024 study conclude that a programme started by government worked in these villages because residents and volunteer groups took it up voluntarily and added their own initiatives, helped by a strong tradition of mutual help. The Kepuharjo study adds practical lessons: release funds in time so training can be held more often, schedule training so that more residents can attend, and explain to residents why preparedness training matters. The 2024 authors also note that the evidence comes from one setting, is based on memories and perceptions, and covers only this programme.
The study behind this case reports no implementation challenges; its authors list only research limitations. The challenges below come from the other sources reviewed and mostly concern Kepuharjo:
Funds for training arrive late because village fund reporting has to be completed first, so training is held once a year and not monthly. Residents were not equally keen: some did not see why the training mattered, and sessions fell on weekdays, so not everyone could attend. Equipment was missing, including handheld radios for households, evacuation vehicles and some training equipment. Communication is hard because there are no landlines and the signal near the volcano is unstable.
Reported responses are limited. Tents and a communal kitchen vehicle were provided by the village hall and by Tagana, and the sister-village arrangement lets safer villages receive evacuees. Beyond this, no adaptive strategy for the funding delays or the attendance problem was found in the sources reviewed.
A further difficulty before the programme took hold was that many slope residents resisted relocation until about 2012, because land ties them to the area, according to the study.
No formal risk and mitigation plan for the programme was found in the sources reviewed. Based on the available information, the following risks for a similar programme can be inferred, with mitigation measures that match what is reported:
Dependence on government funding and slow release of funds could make training irregular; a multi-year training budget and an agreed release schedule would reduce this. Volunteer fatigue or turnover could weaken the teams; rotating tasks, regular small meetings through the district forum and recognised roles would help. Uneven participation, for example when training falls on working days, could leave out residents; offering sessions at different times and explaining the purpose to residents would widen reach. Gaps in communication and transport equipment could undermine an evacuation; pooling equipment through hamlet-level lists and agreements with neighbouring villages, as already done in Kepuharjo, reduce this risk. Unclear chains of command between agencies, village teams and volunteers could cause confusion during an evacuation; a written coordination structure and joint drills would help.
Risk & Mitigation Plan
Scalability and Sustainability
The programme is kept going by regency and village budgets, by the standing role of the regency disaster agency, and by volunteers who give their time. In Kepuharjo the village team rests on a formal village decree. Volunteer groups and the district forum continue between events, and communal work and local custom support participation. The model is exposed to funding delays and to volunteer turnover, and no source describes a long-term funding plan, a succession plan for volunteers, or a review cycle.
Within Sleman Regency the resilient village model has been repeated widely: 53 villages had been formally confirmed by September 2019. What scales is the structure: a village team with defined divisions, linked volunteer groups, a forum that connects them with the regency agency, and a routine of training and drills. What must be adapted is the hazard-specific content (evacuation routes, shelters, warning signs), the funding arrangement and the use of local custom, which the study treats as a key support in these villages.
The programme relies on simple, robust tools: handheld radios, monitoring posts with lighting and loudspeakers, community radio and word of mouth. No digital platform or software is described. The sources show handheld radios are not available to every household in Kepuharjo.
No public information on the programme's set-up costs was found in the sources reviewed. The only figure is a budget of 150 million rupiah for resilience training in Kepuharjo, reported in a 2018 study as budgeted for the year, with actual spending not stated. Based on the resources required, the direct costs of a similar programme would cover: setting up the village team and its divisions; initial training and simulation exercises; risk mapping and contingency planning; evacuation signs, routes and gathering points; shelter and public kitchen equipment; and communication equipment such as handheld radios, loudspeakers and community radio.
No operating budget was found in the sources reviewed. Recurring costs would include annual or more frequent training with transport allowances, meetings of the district forum, upkeep of monitoring posts, radios and vehicles, replacement of shelter supplies, and coordination time of agency staff. Volunteer labour is unpaid according to the sources, but it has a hidden cost in time and may need small allowances to hold on to volunteers.
A government-started structure lasts when it is anchored in a formal decision (such as a village decree), when volunteer groups and local custom already offer a base, and when funds arrive on time.